The useful question is not “What deposit percentage do businesses charge?” It is “What cash must be available before the next reliable receipt?” A deposit percentage without a dated cost schedule cannot answer that.
List payments in date order
Consider a 10,000 project with 1,000 of existing cash assigned to it. A proposed deposit is 3,000. The example assumes that deposit clears before any job payments, and that the assigned cash is not also promised to another job.
| Event | Cash movement | Project cash after event |
|---|---|---|
| Assigned cash plus collected deposit | +4,000 | 4,000 |
| Materials paid, week 1 | −3,500 | 500 |
| Labour and other payments, week 2 | −2,000 | −1,500 |
| Milestone collected, week 3 | +4,000 | 2,500 |
| Remaining delivery payments, week 4 | −1,500 | 1,000 |
| Final payment collected | +3,000 | 4,000 |
The project generates 3,000 above its 7,000 cash outflows, but it still requires 1,500 of temporary funding in week 2. The final balance includes the original 1,000; it is not all profit.
Calculate the deposit needed for this schedule
Payments before the first milestone total 5,500. With 1,000 assigned cash and no buffer, the opening receipt needed is 5,500 − 1,000 = 4,500, or 45% of the contract amount. If the deposit rises to 4,500 while the milestone stays at 4,000, the final payment must fall to 1,500 to keep total receipts at 10,000.
This is a funding requirement under the stated schedule, not a recommended or legally permissible deposit. Sector and location rules may limit deposits; payment rights and refund obligations depend on applicable terms. Another approach is to move an agreed milestone earlier or negotiate a later supplier payment.
Use cash before the next milestone with assigned cash 1,000, deposit 3,000, materials 3,500, labour 2,000 and other payments zero. It returns the 1,500 shortfall. The tool aggregates one interval; the table checks when cash reaches its lowest point.
Test timing, not just totals
If the week-3 milestone arrives after the remaining 1,500 payment, the deficit reaches 3,000 instead. A correct invoice due date is not evidence that the receipt will clear that day. Keep an expected date and a delayed case.
Record milestones by observable completion conditions, with the amount and payment timing made clear. The government payment-terms reference explains the role of clear timing and payment methods; it does not endorse this example’s percentages. Transfer the schedule into your cash forecast before using available cash elsewhere.
Method and scope
All amounts above are hypothetical teaching figures in one currency, excluding tax unless stated otherwise. These are original scenarios, not market prices, benchmark targets or professional recommendations. The references support the underlying concepts, not the example assumptions. This AI-assisted explanation has not had independent professional review. Calculation methods and limitations.
Frequently asked questions
Is a 30% deposit enough?
It depends on dated outflows, other available cash and when the next receipt clears. In this example 30% leaves a 1,500 shortfall.
Can I count an unpaid deposit as cash?
No. Keep an expected deposit in the forecast, but distinguish it from cash already available. Test what happens if it is late.